Thursday, 12 February 2009

HCT Phase 01 Info




Attached précis of the scheme (sans snow, ahem...)

4 comments:

  1. Would we be able to get a cost/m2 for both the new build and the refurbishment for this scheme? It would be a useful comparative - and allow us to show the school a sliding scale of what you get for your money.

    ReplyDelete
  2. Sure:

    The LRC was approx £1205/m2
    The Workshops roughly £1110/m2

    ReplyDelete
  3. Sure:

    The LRC was approx £1,205/m2
    and the Workshop £1,110/m2

    ReplyDelete
  4. The LRC is the refurb of course, but the much higher standard of finish / fit-out accounts for the extra cost compared to the workshop building.

    The savings achieved for re-use of the existing structure (as opposed to new build steel) were c.£750k (15%).

    The sector average at the time of construction was £1650/m2.

    ReplyDelete